Planning Application
24/03645/FULL1
Woodhayes, 76A The Avenue, Beckenham, BR3 5ES
Full / Other PlanningBeckenham Town & Copers Cope ward
Submission
30 Sep 2024
Target
18 Feb 2025
Decision
27 Feb 2025
Outcome
Approved
Committee decisionApproved
27 Feb 2025Loading map…
Scheme description
Demolition of existing houses and the construction of 6 homes together with the construction of a new access road, car parking spaces, bin and cycle stores and new hard and soft landscaping.
Parties
Timeline
30 Sep 2024
Application submitted
15 Oct 2024
Application validated
27 Feb 2025
Committee decision: Approved
Supporting documents · 67
1–25 of 67
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE10 Nov 2024View ↗
EXISTING/PROPOSED SECTION A-A30 Sep 2024View ↗
EXISTING/PROPOSED SECTION A-A15 Oct 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE11 Nov 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE1 Nov 2024View ↗
NEIGHBOUR COMMENT (OBJECTION) SUBMITTED ONLINE28 Oct 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE9 Nov 2024View ↗
PLOTS 4-6 PROPOSED ELEVATIONS30 Sep 2024View ↗
REDACTED SUPPORT COMMENT13 Nov 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE5 Nov 2024View ↗
PLANNING ADDENDUM (NEW NPPF)18 Dec 2024View ↗
PROPOSED BLOCK PLAN30 Sep 2024View ↗
PRELIMINARY DRAINAGE STRATEGY REPORT23 Jan 2025View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE5 Nov 2024View ↗
PROPOSED STREET SCENE30 Sep 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE11 Nov 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE11 Nov 2024View ↗
FIRE STATEMENT30 Sep 2024View ↗
DESIGN AND ACCESS STATEMENT30 Sep 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE23 Oct 2024View ↗
ARBORICULTURAL IMPACT ASSESSMENT AND METHOD STATEMENT30 Sep 2024View ↗
FLOOD RISK ASSESSMENT30 Sep 2024View ↗
REDACTED SUPPORT COMMENT12 Nov 2024View ↗
LANDSCAPING DETAILS30 Sep 2024View ↗
NEIGHBOUR COMMENT (SUPPORT) SUBMITTED ONLINE7 Nov 2024View ↗
Summary
Reference
24/03645/FULL1
Type
Full planning permission
Applicant
Mr J Miller
Submitted
30 Sep 2024
Decision date
27 Feb 2025
Officer
—
Council
Decision
Approved
Decision route
Committee
How long, really
21
wks · this application
Submission → decision · 13 wks over the 8-week target
Public response
Objections
7
In support
31
Total comments
41