Planning Application
24/00218/FULL1
57 Kangley Bridge Road, Lower Sydenham, London, SE26 5BA
Full / Other PlanningPenge & Cator ward
Submission
19 Jan 2024
Target
6 Mar 2024
Decision
13 Jun 2024
Outcome
Approved
Committee decisionApproved
13 Jun 2024Loading map…
Scheme description
Demolition of existing building and redevelopment of site for industrial processes (Use Class E(g)(iii)); industrial (Use Class B2); and/or storage and distribution (Use Class B8)) purposes, with ancillary offices and associated parking, servicing, access arrangements and other associated works.
Parties
Timeline
19 Jan 2024
Application submitted
1 Feb 2024
Application validated
13 Jun 2024
Committee decision: Approved
Supporting documents · 64
1–25 of 64
PLANTING PLAN18 Jan 2024View ↗
BREEAM PRE-ASSESSMENT REPORT18 Jan 2024View ↗
EXISTING ELEVATIONS (NORTH AND WEST)18 Jan 2024View ↗
URBAN GREENING FACTOR18 Jan 2024View ↗
GROUND INVESTIGATION REPORT H18 Jan 2024View ↗
PROPOSED ROOF PLAN18 Jan 2024View ↗
LAND CONTAMINATION ASSESSMENT18 Jan 2024View ↗
TYPICAL GREEN ROOF CYCLE SHELTER DETAIL18 Jan 2024View ↗
GROUND INVESTIGATION REPORT J18 Jan 2024View ↗
BIODIVERSITY NET GAIN REPORT18 Jan 2024View ↗
TRANSPORT STATEMENT18 Jan 2024View ↗
PROPOSED ELEVATIONS (NORTH & SOUTH)18 Jan 2024View ↗
Acknowledgement Letter6 Feb 2024View ↗
NOISE IMPACT ASSESSMENT18 Jan 2024View ↗
TREE PROTECTION PLAN18 Jan 2024View ↗
PROPOSED CROSS SECTION SHEET 118 Jan 2024View ↗
PROPOSED LGF, GF & 1F CORE PLANS18 Jan 2024View ↗
EXISTING LOWER GROUND FLOOR PLAN18 Jan 2024View ↗
EXISTING GROUND FLOOR PLAN18 Jan 2024View ↗
GROUND INVESTIGATION REPORT D18 Jan 2024View ↗
PROPOSED SITE PLAN- GF18 Jan 2024View ↗
DESIGN AND ACCESS STATEMENT PART 218 Jan 2024View ↗
EXISTING SITE SECTIONS SHEET 118 Jan 2024View ↗
TREE CONSTRAINTS PLAN18 Jan 2024View ↗
LIGHTING ASSESSMENT REPORT18 Jan 2024View ↗
Summary
Reference
24/00218/FULL1
Ward
Type
Full planning permission
Applicant
Mr Ewen McLeod
Submitted
19 Jan 2024
Decision date
13 Jun 2024
Officer
—
Council
Decision
Approved
Decision route
Committee
How long, really
21
wks · this application
Submission → decision · 13 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0