Planning Application

25/3301

Southover Partnership School, Kingsbury Road, London, NW9 9HA

Listed BuildingQueensbury wardNotifiable Pipeline (Gas)
Submission
25 Nov 2025
Target
4 Feb 2026
Decision
4 Feb 2026
Outcome
Approved
Delegated decisionApproved
4 Feb 2026
Decided by Gary Murphy under delegated powers
Loading map…
Scheme description

Listed Building Consent for proposed installation of 3x connected single-storey mobile classroom units and adjacent astroturf and rubber flooring play areas within the curtilage of School

Parties
Applicant
The Southover Partnership
Timeline
25 Nov 2025
Application submitted
4 Feb 2026
Delegated decision: Approved
Supporting documents · 11
Final delegated report4 Feb 2026View ↗
Final decision notice4 Feb 2026View ↗
Existing floor plan26 Nov 2025View ↗
Existing site plan26 Nov 2025View ↗
Existing location plan26 Nov 2025View ↗
Pre-existing & existing north elevation26 Nov 2025View ↗
Pre-existing & existing south elevation26 Nov 2025View ↗
Pre-existing & existing west elevation26 Nov 2025View ↗
Pre-existing site plan26 Nov 2025View ↗
Pre-existing location plan26 Nov 2025View ↗
Application form26 Nov 2025View ↗
View Application Page ↗
Data from the Brent planning register.
Summary
Reference
25/3301
Type
Listed Building Consent
Applicant
The Southover Partnership
Submitted
25 Nov 2025
Decision date
4 Feb 2026
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
10
wks · this application
Submission → decision · 2 wks over the 8-week target
Public response
Objections
1
In support
0
Total comments
2