Phase 3A (Block N) - Land Former Ace Corner, North Circular Road, Stonebridge, London, NW10 7UD

Discharge of ConditionsAlperton wardNot Available: Strategic Ind Locations/Local Ind Sites
Submission
23 Nov 2023
Target
18 Jan 2024
Decision
19 Feb 2024
Outcome
Approved
Delegated decisionApproved
19 Feb 2024
Decided by Sean Newton under delegated powers
Loading map…
Scheme description

Details pursuant to condition 15 (landscaping) of Variation of Conditions reference 19/2732 dated 4 October, 2019, for Minor material amendment under Section 73 of the Town and Country Planning Act 1990 to vary the wording of condition 6 (outline approved drawings) to allow: An increase in the proposed parameter height for Plot E to a maximum between 86.60m AOD ? 92.90m AOD of Outline Planning Permission reference 18/0321 dated 28 September, 2018 for Hybrid planning permission for the redevelopment of the former Northfields Industrial Estate: Outline planning permission for the demolition of existing buildings and structures on the site, all site preparation works and redevelopment to provid

Parties
Applicant
SEGRO V-Park Grand Union LLP
Agent
Quod
Timeline
23 Nov 2023
Application submitted
19 Feb 2024
Delegated decision: Approved
Supporting documents · 13
Final delegated report19 Feb 2024View ↗
Final decision notice19 Feb 2024View ↗
Terrace lighting layout23 Nov 2023View ↗
External lighting layout site plan23 Nov 2023View ↗
External works levels & setout plan sheet 1 of 223 Nov 2023View ↗
External works levels & setout plan sheet 2 of 223 Nov 2023View ↗
Planting layout23 Nov 2023View ↗
Roof terrace layout23 Nov 2023View ↗
Hard landscaping and external furniture-23 Nov 2023View ↗
Finishes-roof terrace23 Nov 2023View ↗
Landscape management plan23 Nov 2023View ↗
Cover letter23 Nov 2023View ↗
Application form23 Nov 2023View ↗
View Application Page ↗
Data from the Brent planning register.
Summary
Reference
23/3678
Type
Conditions pursuant to a full permission
Applicant
SEGRO V-Park Grand Union LLP
Submitted
23 Nov 2023
Decision date
19 Feb 2024
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
13
wks · this application
Submission → decision · 5 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0