Planning Application
23/00892/ALA04
Riverside Energy From Waste Facility Norman Road Belvedere Kent DA17 6JY
OtherBELVEDERE wardArticle 10 Direction: Multiple
Submission
18 Apr 2024
Target
9 May 2024
Decision
8 May 2025
Outcome
Other
Delegated decisionOther
8 May 2025Decided by Ian Smith under delegated powers
Loading map…
Scheme description
Application by Cory Environmental Holdings Limited (CEHL) for an Order Granting Development Consent for the Cory Decarbonisation project (EN010128)
Timeline
18 Apr 2024
Application submitted
8 May 2025
Delegated decision: Other
Supporting documents · 11
WRITTEN REPS REPORT8 May 2025View ↗
LOCAL IMPACT REPORT8 May 2025View ↗
DEADLINE 2 RESPONSE8 May 2025View ↗
DEADLINE 3 RESPONSE8 May 2025View ↗
DEADLINE 4 RESPONSE8 May 2025View ↗
DEADLINE 5 RESPONSE8 May 2025View ↗
DEADLINE 6 RESPONSE8 May 2025View ↗
DEADLINE 6 RULE 17 RESPONSE8 May 2025View ↗
RULE 6 LETTER9 Oct 2024View ↗
S56 NOTIFICATION8 May 2024View ↗
APPLICATION DETAILS2 May 2024View ↗
View Application Page ↗
Data from the Bexley planning register.
Summary
Reference
23/00892/ALA04
Ward
Type
Adjoining Local Authority Consultation
Applicant
Cory Environmental Holdings Limited
Submitted
18 Apr 2024
Decision date
8 May 2025
Officer
Council
Decision
Other
Decision route
Delegated (officer)
How long, really
55
wks · this application
Submission → decision · 47 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0