Development Intent
Planning AtlasBarnetGolders GreenApplication
Planning Application

26/0427/HSE

92 Princes Park Avenue London NW11 0JX

HouseholderGolders Green wardCritical Drainage Area: CDA_018 - Decoy Brook
Submission
4 Feb 2026
Target
6 Apr 2026
Decision
27 Apr 2026
Outcome
Approved
Delegated decisionApproved
27 Apr 2026
Decided by Andrew Turner under delegated powers
Loading map…
Scheme description

Part single, part two storey side and rear extensions with 3no. rooflights. Partial conversion of the existing garage. Alterations to front bay windows and introduction of new front bay windows. New front entrance including new roof canopy and columns with associated ramp. Alterations to existing fenestration and decorative detailing to elevations including brick slips and stone plinth. New side windows. Roof alteration and extension including roof lights, and side and rear dormer windows balconies and 1.8m privacy screen to both rear dormers. Installation of solar panels [AMENDED DESCRIPTION]

Timeline
4 Feb 2026
Application submitted
9 Feb 2026
Application validated
27 Apr 2026
Delegated decision: Approved
Supporting documents · 17
DN: APPROVE HSE WITH CONDS27 Apr 2026View ↗
FULL SET OF REVISED DRAWINGS (APPROVED)27 Mar 2026View ↗
SUPPORTING STATEMENT REVISION A227 Mar 2026View ↗
APPLICATION FORM - WITHOUT PERSONAL DATA4 Feb 2026View ↗
THE LOCATION PLAN4 Feb 2026View ↗
EXISTING BLOCK PLAN4 Feb 2026View ↗
EXISTING GROUND FLOOR4 Feb 2026View ↗
EXISTING FIRST FLOOR4 Feb 2026View ↗
ROOF PLAN - EXISTING4 Feb 2026View ↗
ELEVATION (FRONT) - EXISTING4 Feb 2026View ↗
ELEVATION (REAR) - EXISTING4 Feb 2026View ↗
ELEVATION (SIDE) - EXISTING4 Feb 2026View ↗
ELEVATION (SIDE) - EXISTING4 Feb 2026View ↗
SECTION - EXISTING4 Feb 2026View ↗
SECTION - EXISTING4 Feb 2026View ↗
COMMUNITY INFRASTRUCTURE LEVY - COMPLETED FORM4 Feb 2026View ↗
FLOOD RISK ASSESSMENT4 Feb 2026View ↗
View Application Page ↗
Data from the Barnet planning register.
Summary
Reference
26/0427/HSE
Type
Householder Application
Applicant
Zak Ahad
Submitted
4 Feb 2026
Decision date
27 Apr 2026
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
12
wks · this application
Submission → decision · 4 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0