Planning Application
21/02125/FULL
Land Off The A124, Barking, Barking And Dagenham, IG11 8JH
Full / Other PlanningAbbey ward
Submission
24 Nov 2021
Target
2 Sep 2022
Decision
30 Aug 2022
Outcome
Approved
Delegated decisionApproved
30 Aug 2022Decided by Olivia St-Amour under delegated powers
Loading map…
Scheme description
Construction of a new above ground decentralised energy centre and visitor centre and associated buried heat network piping within the site, landscaping, parking, new site access, boundary treatments and illuminated external display. The Energy Centre building and site compound shall house mechanica
Parties
Timeline
24 Nov 2021
Application submitted
20 Dec 2021
Application validated
30 Aug 2022
Delegated decision: Approved
Supporting documents · 50
1–25 of 50
DATED DECISION NOTICE30 Aug 2022View ↗
Completed Legal Agreement- 30.08.202230 Aug 2022View ↗
Committee Report - Energy Centre - April 20224 May 2022View ↗
Site Selection Table - Revised21 Mar 2022View ↗
Applicant Response Letter to Neighbour Representations21 Mar 2022View ↗
Barking Town Centre Decarbonisation Pathway21 Mar 2022View ↗
Transport Statement6 Jan 2022View ↗
Planning Statement20 Dec 2021View ↗
Energy Statement20 Dec 2021View ↗
Townscape and Visual Appraisal - 8124 Nov 2021View ↗
Townscape and Visual Appraisal 7124 Nov 2021View ↗
Townscape and Visual Appraisal - 6224 Nov 2021View ↗
Townscape and Visual Appraisal - 5224 Nov 2021View ↗
Townscape and Visual Appraisal - 4224 Nov 2021View ↗
Townscape and Visual Appraisal - 3124 Nov 2021View ↗
Townscape and Visual Appraisal - 2124 Nov 2021View ↗
Townscape and Visual Appraisal - 1224 Nov 2021View ↗
Statement of Community Involvement24 Nov 2021View ↗
Outline Construction Logistics Plan - 124 Nov 2021View ↗
Heritage Statement24 Nov 2021View ↗
Fire Statement24 Nov 2021View ↗
Daylight Sunlight Report24 Nov 2021View ↗
Cover Letter24 Nov 2021View ↗
Flood Risk Assessment and Outline Drainage Stratergy24 Nov 2021View ↗
Outline Site Waste Management Plan24 Nov 2021View ↗
View Application Page ↗
Data from the Barking And Dagenham planning register.
Summary
Reference
21/02125/FULL
Ward
Type
Full Planning Permission
Applicant
Not disclosed
Submitted
24 Nov 2021
Decision date
30 Aug 2022
Officer
Council
Decision
Approved
Decision route
—
How long, really
40
wks · this application
Submission → decision · 32 wks over the 8-week target